Six workers, all working at the same rate, build a wall in 10 days. How many days would 4 such workers take to build the same wall?

Answer: 15

The job takes 6 × 10 = 60 worker-days. With 4 workers: 60 ÷ 4 = 15 days.

Common wrong answers

If you answered 8
8 subtracts 2 days for 2 fewer workers.
If you answered 24
24 multiplies 4 by 6.
If you answered 6.67
6.67 scales the time down as if fewer workers were faster.